The November AI Capex Tracker went up on November 1 with one finding at the top: Amazon, Alphabet, Microsoft, Meta and Oracle spent $237.3 billion on capital projects in their latest quarter, and three of them now spend more than their businesses bring in as operating cash. This is the mid-month update. The capex figures haven’t moved, because nobody big reports again until late January. What moved is everything around them. The spenders went to the bond market for about $67 billion in a week and paid more for it than they did earlier in the year. CoreWeave reported. Nvidia lost its chief executive five days before its own report. And the November 3 midterms put a large share of planned US data center capacity in states whose incoming governors want to pause it.
What changed since November 1
| Item | November 1 tracker | Now |
|---|---|---|
| Five-spender quarterly capex | $237.3B | Unchanged; next reports late January |
| Microsoft funding | Debt markets untapped | $25B of bonds on October 29, its first US sale since 2017 |
| Hyperscaler bonds since October 29 | n/a | About $67B in five deals, plus $10B of Oracle stock and $3.8B of Alphabet Asian bonds |
| CoreWeave | Q2 capex $9.4B, year $35B to $39B | Q3 capex $14.5B, year $37B to $39B, backlog $132.5B |
| Nvidia | Reports November 17 against a $108B guide | Same date; Jensen Huang resigned November 12, Colette Kress is interim CEO |
| Data center permitting | Local fights | About 40% of pending US capacity sits in states with governors-elect pledged to stop or pause it |
The borrowing week
Between October 29 and November 4 four of the five spenders sold bonds. Microsoft went first with $25 billion in ten tranches, drew more than four times that in orders, and became the last member of the group to borrow for the build. That matters for the tracker because Microsoft was the one company on November 1 still paying for its data centers out of income. It still could. It chose not to. Alphabet followed with €6 billion in seven euro tranches on November 2, then about $3.8 billion in its first Hong Kong and Singapore dollar bonds, upsized from a $3 billion target and settling November 19. Oracle priced $10 billion of notes and $10 billion of new shares the same night. Meta sold $15 billion in dollars on November 3 and €9 billion in euros the next day, its first euro deal, on a record €53 billion order book.
Orders were plentiful. The price went up. Every repeat borrower paid more than the last time it came to market, and the gap is widest for the weakest balance sheet.
| Issuer | Date | Raised | Terms | What it tells you |
|---|---|---|---|---|
| Microsoft | Oct 29 | $25B bonds | Ten tranches, 2 to 40 years, fixed coupons 4.85% to 6.35%, AAA | Even the cash-funded spender wants outside money now |
| Alphabet | Nov 2 and Nov 19 | €6B plus about $3.8B | 2045 euro notes at 185bp over mid-swaps against 125bp in May | First Hong Kong and Singapore dollar bonds, after dollar, euro, sterling and Swiss franc sales earlier in the year |
| Oracle | Nov 2 | $10B bonds plus $10B stock | Coupons 7.00% to 8.65%, 240bp to 335bp over Treasuries; shares sold 11.2% below the prior close | Used its whole $20B FY27 to FY30 funding cap five days after setting it |
| Meta | Nov 3 and Nov 4 | $15B plus €9B | 2056 notes at 220bp over Treasuries, about 90bp wider than April | Says it won’t return to unsecured markets before the second quarter of 2027 |
Oracle is the clearest case. It told investors at its October 28 investor day that new capital-markets money for the whole FY27 to FY30 cycle would stop at $20 billion, split between debt and equity. It raised all $20 billion the following Monday. The notes carry a weighted coupon of about 7.8%, which works out to roughly $780 million a year of interest on $10 billion, and the stock fell almost 9% on the day. Meta’s deal says something different. A double-A company paid close to a point more over Treasuries on its longest bond than it did in April, with S&P’s outlook already moved to negative. The money is there. It just costs more each round, and the order books are no longer what sets the price.
There’s a second layer under the bonds. Moody’s counts about $1.2 trillion of data center leases across Microsoft, Amazon, Alphabet, Meta, Oracle and CoreWeave, and about $820 billion of that hasn’t reached a balance sheet yet because the buildings are still going up. The bond sales are the visible part of the funding. The leases are the part that lands later.
CoreWeave: the quarter got pulled forward
| CoreWeave, Q3 2026 | Value | Year ago or prior guide |
|---|---|---|
| Revenue | $3.66B | $1.36B, up 168% |
| Capex | $14.51B | $1.85B a year ago |
| Operating cash flow | About $2.0B | |
| Net interest expense | $846M | Against $379M adjusted operating income |
| Backlog | $132.5B | $104.2B in June, $55.6B a year ago |
| 2026 capex guide | $37B to $39B | $35B to $39B, low end raised |
| Debt and cash | Nearly $47B debt, $4.12B cash | Q4 interest guided at $1.05B to $1.15B |
The headline was a beat and a raise, and the stock rose about 25% the next day. The capex line tells a quieter story. CoreWeave spent $30.65 billion in nine months, so the $37 billion to $39 billion year leaves only $6.4 billion to $8.4 billion for the December quarter, roughly half of what it just spent. Management raised the low end because it is handing infrastructure to customers sooner than planned. So spending that was meant for the fourth quarter happened in the third. That’s good for revenue timing. It also means the year’s capex number didn’t really grow, and anyone extrapolating $14.5 billion a quarter into 2027 is ahead of the company. Management said that if it builds only for signed backlog, 2027 capex would land roughly in line with 2026.
Interest is the other line to watch. CoreWeave paid $846 million of net interest in the quarter, more than twice its adjusted operating income, and guides $1.05 billion to $1.15 billion for the next one. Revenue growth is real, and the $132.5 billion backlog says demand is real too. The equity still depends on the cost of the debt. More detail is in the CoreWeave Q3 analysis.
Suppliers: still running hot
| Supplier | Latest data | Value | Growth | Read |
|---|---|---|---|---|
| TSMC | October revenue | NT$586.9B | +59.7% y/y, +14.7% m/m | Record month; about 34% to 35% of the Q4 guide in one month |
| Applied Materials | Fiscal Q4 to Oct 25 | $10.41B | +53% | Guides $11.1B, plus or minus $0.5B; adding capacity to double output by 2028 |
| Nvidia | Fiscal Q3 to Oct 25, reports tonight | Guide $108.0B, plus or minus 2% | Consensus about $109B | Data center estimates run $99.7B to $110.8B against $89.0B last quarter |
TSMC’s October alone covered about a third of its $52.3 billion to $54.3 billion quarterly guide, which puts it on pace for the top of the range. Applied Materials guided above consensus at the midpoint and said it is building capacity to double equipment output from current levels by 2028. Equipment makers don’t plan that kind of expansion for a one-year spike. Nothing in the supply chain has turned yet.
Nvidia reports after the US close today, Tuesday, November 17. The board accepted Jensen Huang’s resignation on November 12, named CFO Colette Kress interim CEO and Harvey Jones as the company’s first board chair, and has since said through people familiar with its thinking that it isn’t considering bringing him back. None of that changes the quarter being reported. It does change who gives the outlook for the next one, and the Nvidia guide is the single best read on how much of the 2027 capex the hyperscalers have already talked about is turning into orders.
The new risk: permits
The November 3 midterms added a constraint the tracker didn’t carry two weeks ago. According to Cleanview data reported by Bloomberg, about 40% of pending US data center capacity is planned in states where newly elected governors campaigned on stopping or pausing data center construction. Texas is the biggest single exposure, with about 124 gigawatts of operating and planned capacity.
| State | Governor-elect position | Open question |
|---|---|---|
| Texas | Gina Hinojosa pledged a moratorium on new data center approvals until the Legislature passes new rules | Whether permitted projects, signed power contracts and sites under construction are covered |
| Georgia | Keisha Lance Bottoms pledged a statewide moratorium on new construction | Scope and legal route |
| Ohio, Michigan, New Mexico | Governors-elect campaigned on a stop or pause | Timing after inauguration |
| New York, Oregon | Pledged to extend pauses already in place | Duration |
Voters in at least 33 communities also backed local restrictions, and Democrats will control both chambers of Congress from January. Most of these pledges target new approvals, and most of the capex on the scoreboard is going into sites that are already permitted, powered or under construction, so the 2026 and early 2027 numbers are mostly locked in. The exposure is in the 2028 and later pipeline, which is exactly the spending the companies have told investors will keep rising. A pause in Texas or Georgia won’t cut capex. It moves it to other states, adds months to grid studies and pushes up the price of sites that already have power.
What to watch through December
| Date | Event | The number that matters |
|---|---|---|
| November 17 | Nvidia fiscal Q3 | Data center revenue against $89.0B last quarter, and the Q4 guide under an interim CEO |
| November 24 | Dell fiscal Q3 | How fast its roughly $95B AI server backlog turns into revenue and cash |
| Early December | Broadcom fiscal Q4 | AI semiconductor revenue against $21.7B |
| Mid December | Oracle fiscal Q2, Micron fiscal Q1 | Oracle’s capex pace against $90B to $95B after the $20B raise; Micron revenue against about $61.5B |
| January | New governors take office; Texas Legislature convenes | The legal text of any moratorium, and whether it covers permitted projects |
| Ongoing | Secondary trading in the new bonds | Whether Oracle’s 2046 notes and Meta’s 2056 notes hold their issue spreads |
Bottom line
Two weeks after the November tracker the spending numbers are unchanged and the conditions around them are tighter. The hyperscalers raised about $67 billion of bonds in a week, Oracle added $10 billion of stock, and every repeat borrower paid a wider spread than earlier in the year, from about 60 basis points more for Alphabet to as much as 175 more for Oracle. Microsoft, the last one funding the build from income, borrowed too. CoreWeave beat and raised, but its third quarter pulled forward spending from the fourth, and its interest bill now runs at more than twice its adjusted operating income. The supply chain hasn’t flinched: TSMC had a record October and Applied Materials is building capacity to double output by 2028. Two new risks arrived. Nvidia reports tonight without the founder who built it, and the midterms put about 40% of the pending US data center pipeline in states whose incoming governors want to pause it. For a decision maker this means the 2026 spend is effectively locked and the suppliers keep pricing power into 2027. The risk has moved into two places: the price of the debt that funds the build, and the permits for the projects that come after 2027. Watch Nvidia’s guide tonight, the secondary spreads on the November bonds, and the wording of the Texas moratorium in January.
Method: capex as each company reports it, as in the November 1 tracker. Bond spreads compare November pricing with each issuer’s earlier 2026 deal at similar maturities. Euro amounts converted at about $1.12. The full AI Capex Tracker is updated monthly; the next full edition follows the late-January hyperscaler reports.